Agenda · Reviews & approvals
Review engineering change requests one at a time: impact on cost, schedule, quality and safety, a phone vote per request and a written decision record.
Free to open and edit. Running it live needs Pro, free for 14 days on every new account.
A change control board (CCB) is the group that approves or rejects changes to a controlled baseline such as drawings, specifications or a schedule. This 60-minute agenda reviews engineering change requests one at a time with an impact matrix and a vote, then records conditions, owners and the effective point for each decision.
01Inside
By the end of this meeting, every change request on the docket has an impact assessment and a recorded decision: approved, approved with conditions, rejected, deferred or sent back. Every block in order, with the facilitator's tips.
02Why it works
8 minutes of updates with a visible clock. In a video call the speaker is spotlighted and the room is muted, so nobody talks over them.
35 minutes of open floor with a countdown everyone can see, and a talk-balance meter so the loudest voice doesn't take all of it.
One tap each on a phone, live bars on the screen. A tick shows who has voted, never what they chose.
Capture the decision and its owner with one click while it's said. It lands in the summary, word for word.
Decisions and actions are read back, the summary is already written, and a finish on time earns the confetti.
03In the room
The shared screen, every phone and the summary afterwards, drawn from this template.
On the shared screen
Each block runs on its own timer on the shared screen, and the video call changes with each block, so the meeting keeps to time.
On every phone
People scan the code or tap their invite and answer in the phone's browser. No app to install, no account to make.
Afterwards
Decisions and actions are captured as they're said. When the meeting ends, everyone gets the summary, and one link shares it.
04How to run it
Circulate the docket and each change request with its impact assessment at least two days before the board.
Take safety and regulatory changes first, then by impact. Send incomplete requests back rather than debating them.
Walk every row of the impact matrix for each request; a blank row means nobody has checked.
Vote on each request separately. Agendiq's summary records each decision with the votes for the change log.
Close only when every approved change has an owner and an effective point, and tell requesters the outcome the same day.
05Questions
Still deciding?
Run your next meeting on it. Every new account gets Pro free for 14 days, no card.
It reviews proposed changes to a controlled baseline, assesses their impact on cost, schedule, quality and safety, and decides whether to approve, reject or defer them, keeping a record of each decision.
A formal request to change a released design, drawing, specification or process. It describes the problem, the proposed change and the reason, and the CCB assesses its impact before deciding.
Representatives of the functions a change affects, such as engineering, quality, production or construction, procurement and the project manager, with a chair who has decision authority.
Keep going
Change anything in the editor. When you're ready, press Run live: everyone joins with a scan and answers on their phone.
Free forever · Pro free for 14 days · No card needed · Guests never sign up
Change control board meetingRuns with Pro