A go/no-go meeting that walks the readiness checklist, from defects and data migration to cutover and rollback, then takes each lead's call.
Free to open and edit. Running it live needs Pro, free for 14 days on every new account.
A go-live readiness meeting, or go/no-go meeting, decides whether a system launch goes ahead as planned. This 60-minute agenda walks the go-live checklist, including testing, data migration, the cutover plan and rollback, support and training, then takes an anonymous readiness poll and each lead's call before the sponsor decides.
01Inside
By the end of this meeting, the sponsor decides go, go with conditions, or no-go, based on a checked readiness list and each lead's call. Every block in order, with the facilitator's tips.
02Why it works
41 minutes of updates with a visible clock. In a video call the speaker is spotlighted and the room is muted, so nobody talks over them.
7 minutes of open floor with a countdown everyone can see, and a talk-balance meter so the loudest voice doesn't take all of it.
One tap each on a phone, live bars on the screen. A tick shows who has voted, never what they chose.
Capture the decision and its owner with one click while it's said. It lands in the summary, word for word.
Decisions and actions are read back, the summary is already written, and a finish on time earns the confetti.
03In the room
The shared screen, every phone and the summary afterwards, drawn from this template.
On the shared screen
Each block runs on its own timer on the shared screen, and the video call changes with each block, so the meeting keeps to time.
On every phone
People scan the code or tap their invite and answer in the phone's browser. No app to install, no account to make.
Afterwards
Decisions and actions are captured as they're said. When the meeting ends, everyone gets the summary, and one link shares it.
04How to run it
Agree the go/no-go criteria at least a week before, and circulate the readiness checklist with evidence for each item.
Walk the checklist in order; any item that fails a criterion is raised before the poll, not after.
Take the anonymous readiness poll, then ask each lead for their call out loud.
Record the decision and conditions in the summary and send it to everyone on the cutover plan.
05Questions
Still deciding?
Run your next meeting on it. Every new account gets Pro free for 14 days, no card.
The step-by-step, hour-by-hour plan for moving from the old system to the new one: tasks, owners, timings, checkpoints, the point of no return and the rollback steps.
Testing sign-off and open defects, data migration results, the cutover and rollback plans, support and hypercare cover, training, communications and sign-off from each business area.
The project sponsor, based on criteria agreed beforehand and a call from each workstream lead.
Keep going
Change anything in the editor. When you're ready, press Run live: everyone joins with a scan and answers on their phone.
Free forever · Pro free for 14 days · No card needed · Guests never sign up
Go-live readiness meetingRuns with Pro