Weekly work planning with the Last Planner System: last week's PPC and miss reasons, constraints cleared in the look-ahead, and reliable commitments by trade.
Free to open and edit. Running it live needs Pro, free for 14 days on every new account.
The Last Planner System is a lean construction method where the people who direct the work plan it together: pull planning to milestones, a look-ahead to clear constraints, and weekly commitments measured by percent plan complete (PPC). This board runs the weekly work plan meeting in 60 minutes with constraints, misses and commitments in view.
01Inside
Weekly work plan with 4 areas, and a 60-minute agenda that runs it.
“Post work that's ready, a constraint in the look-ahead, or last week's miss and its reason”
By the end of this meeting, each trade has reliable commitments for next week, constraints have owners, and we know why last week's misses happened.
02In the room
The shared screen, every phone and the summary afterwards, drawn from this template.
On the shared screen
Ideas land on the board from every phone, with no names on the notes. Then everyone dot-votes what matters most.
On every phone
People scan the code or tap their invite and answer in the phone's browser. No app to install, no account to make.
Afterwards
Decisions and actions are captured as they're said. When the meeting ends, everyone gets the summary, and one link shares it.
03How to run it
Hold it at the same time each week with the foremen who actually direct the work: the Last Planners.
Start with last week's PPC and one reason per miss, so the team learns rather than blames.
Collect ready work, constraints and misses from phones, then clear constraints with owners and dates.
Commit only constraint-free work within capacity. This board goes beyond a plain weekly work planning agenda by keeping constraints, misses and commitments visible week to week.
04Questions
Still deciding?
Run your next meeting on it. Every new account gets Pro free for 14 days, no card.
A production planning system for construction developed by Glenn Ballard and Greg Howell. It links milestone pull planning, a look-ahead plan, weekly work plans and learning from missed commitments.
Planning backwards from a milestone: the trades agree which work must be finished, by whom, for the next task to start, so each hand-off is requested by the trade that needs it.
A short-range plan, often three to six weeks, used to spot and clear constraints (design, materials, access, inspections) before work is due to start.
Percent plan complete: the share of last week's commitments that were fully completed. Teams track it weekly along with the reasons for misses.
Keep going
Change anything in the editor. When you're ready, press Run live: everyone joins with a scan and answers on their phone.